ext_84998 ([identity profile] trinity-gal.livejournal.com) wrote in [community profile] goshkin 2014-06-19 07:08 pm (UTC)

Obviously it depends on number of builders that are going to work on site at the same time....
still to go...insulation, new windows, wiring, central heating plumbing, right?
plastering, painting and flooring can be done fast
1 bathroom usually takes 2.5 weeks at most to get done by 2 people
Will be interesting to see the progress. Hope it's not too full time for you choosing all stuff...